In construction, change orders and delays are common and can harm profit margins. On average, a project experiences 56 change orders and exceeds its schedule by 20%. Scope creep, unexpected site conditions, and informal requests can strain resources and turn profitable projects into liabilities. Successful contractors use five strategies to maintain profitability in these situations.
1. Document Everything—Your Financial Shield
When it comes to protecting your profits, comprehensive documentation is your strongest defense. Too many contractors rely on handshakes and verbal agreements, only to find themselves unable to substantiate legitimate claims later.
"The project that loses money isn't the one with changes—it's the one where changes weren't properly documented," says Michael Turner, a construction management consultant who has analyzed over 300 troubled projects.
Effective documentation includes:
Real-world example: A mid-sized contractor was directed verbally to use premium materials on a commercial renovation. When payment time came, the owner balked at the additional costs. Because the contractor had sent a confirmation email documenting the verbal direction and had photographed the installation process, they successfully recovered the full premium amount—approximately $42,000 that would have otherwise been absorbed as a loss.
2. Master the Art of Proper Notification
Many construction contracts contain strict notification requirements that can completely bar otherwise valid claims if not followed. Understanding and adhering to these requirements is essential for protecting your financial interests.
Essential notification practices:
Pro tip: Create notification templates pre-populated with contract-specific language that your project managers can quickly complete and send when issues arise. This reduces the burden of compliance while ensuring critical deadlines aren't missed in the heat of project challenges.
Real-world example: On a warehouse project, a contractor discovered undocumented underground storage tanks requiring environmental remediation. By providing immediate notification with comprehensive documentation, they secured a change order covering all direct costs, a 30-day time extension, and partial compensation for extended general conditions—preserving an estimated 14% profit margin that would have been completely erased.
3. Analyze Impacts Comprehensively
Successful contractors understand that the true impact of changes and delays extends far beyond the direct costs of additional materials and labor for the changed work itself.
A comprehensive impact analysis includes:
Industry insight: Research indicates that significant changes and delays typically reduce labor productivity by 25-50% on affected activities due to disruption, crowding, out-of-sequence work, and diluted supervision.
Real-world example: A mechanical contractor facing a 45-day delay in accessing work areas documented not just the direct costs of the delay but also the productivity impact of performing exterior work during winter months instead of fall as originally scheduled. By using industry studies on weather impacts combined with their own productivity tracking, they secured compensation for productivity losses, turning a potential financial disaster into a modestly profitable project.
4. Implement Early Warning Systems
The most profitable contractors don't just react to changes and delays—they anticipate them with systematic early warning processes.
Effective early warning systems include:
Pro tip: Establish "trigger points" for escalation. For example, if an RFI remains unanswered after 75% of the contractual response time has elapsed, automatically escalate to the next level of project management.
Real-world example: A contractor implementing a formal constraint tracking system identified a potential six-week delay in elevator installation due to structural steel modifications. By highlighting this issue eight weeks before impact, they were able to collaborate with the design team on an alternative approach that maintained the original schedule while adding only minimal cost—avoiding approximately $95,000 in delay-related expenses.
5. Negotiate Strategically
Even with perfect documentation and analysis, securing fair compensation ultimately requires effective negotiation. Successful contractors approach these discussions strategically rather than adversarially.
Strategic negotiation principles:
Industry insight: Contractors who present well-documented change orders with clear entitlement analysis recover an average of 65-85% of their claimed amounts, while those with poor documentation typically recover less than 40%.
Real-world example: When faced with owner-directed acceleration after weather delays, a contractor prepared a detailed acceleration plan including shift work, overtime, and expedited deliveries. Rather than demanding full compensation upfront, they implemented daily tracking of acceleration costs and provided weekly updates. This transparent approach resulted in recovering 85% of their documented acceleration costs while maintaining the original completion date—preserving both their profit margin and client relationship.
The Path Forward: Building a Systematic Approach
The difference between contractors who consistently maintain profitability despite changes and delays and those who don't isn't luck—it's systematic processes.
Start by implementing these practical tools:
Remember that change order and delay management isn't just a project management function—it's a critical financial management strategy that directly impacts your bottom line.
By implementing these five strategies systematically across your projects, you can transform what many contractors view as unavoidable profit erosion into a competitive advantage that distinguishes your company in the marketplace.